Who authorized Enchanted Rock? This question killed Puerto Rico power deal
Puerto Rico needed electricity. That urgency was real. Years of generation shortages and repeated blackouts made additional power a public priority. Against that backdrop, the Puerto Rico Electric Power Authority pursued a contract for up to 400 megawatts of temporary generation at the Aguirre Power Plant — a deal potentially worth nearly $5.9 billion over 10 years.

TL;DR
- Puerto Rico Electric Power Authority (PREPA) pursued a 10-year contract for up to 400 megawatts of temporary generation, potentially worth $5.9 billion.
- The contract was ultimately revoked by the Financial Oversight and Management Board due to an impaired procurement process.
- A central dispute involves whether Enchanted Rock authorized its participation, with the company claiming its signature was used without authorization.
- The oversight board found that Power Expectations, the lead contractor, did not independently demonstrate the required financial capacity and technical experience.
- Enchanted Rock's participation was crucial for the consortium's perceived ability to deliver, making the authorization question central to the award's validity.
- Months prior, the oversight board had raised concerns about Power Expectations' qualifications and the multi-company seller arrangement.
- The incident exposes a weakness in fragmented government procurement, where responsibility is divided across multiple institutions, leading to a lack of clear ownership of the overall transaction.
- Legislative scrutiny and questions about corporate disclosures are expanding as a result of the contract's collapse.
- The article argues that emergency conditions do not justify skipping basic controls that protect taxpayers, emphasizing the need for clear responsibility in verifying contractor authorization.